I am working with a schedule that is utilizing MSP 2016. The client has asked for a Planned % complete to compare against the % complete. I looked in all the books I have and ended up going on line. The only thing I could find was a you tube video and ended up n using that. But it was based on MSP 2010 & 2013.
My first problem is that the calculation returns an error for the Milestones, but works for the tasks, does anyone know how to get rid of this problem?
My second problem is that if I move the dates out the calculation sends back a negative planned value which has been picked up from the Client and has been rejected.
I am not that familiar with MSP to be honest let alone 2016 so any help would be greatly appreciated. Please see formulas used below
Number column 1
Val(ProjDurConv(Duration,pjDays))
Number column 2
IIf(DateDiff("d",Start,[Status Date])>=Val(ProjDurConv([Baseline Duration],pjDays)),Val(ProjDurConv([Baseline Duration],pjDays)),IIf(DateDiff("d",[Baseline Start],[Status Date])<=0,0,DateDiff("d",Start,[Status Date])))
Number Column 3
Number2/Number1
Text30
format(Number3,"0%")